If you are thinking about extending your home, one of the first questions is whether you need planning permission. The answer is often no. Many single-storey extensions and loft conversions in England can go ahead under permitted development rights, which grant planning permission automatically for certain types of work, as long as you stay within set limits.
This guide explains how those rights work, where they stop, and which other approvals still apply. The rules below are for houses in England at the time of writing. Wales, Scotland and Northern Ireland have their own systems, and the rules do change, so always check the current position on the Planning Portal or with your local planning authority.
What permitted development allows
For a typical house, permitted development rights allow a single-storey rear extension of up to 3 metres deep on a terraced or semi-detached house, or 4 metres on a detached house, with a maximum height of 4 metres. Under the larger home extension scheme, those depths can increase to 6 and 8 metres, but you must notify the council first and neighbours have the chance to comment.
Other conditions usually apply. For example, extensions within 2 metres of a boundary have an eaves height limit of 3 metres, materials should be similar in appearance to the existing house, and extensions cannot cover more than half the land around the original house.

When permitted development does not apply
Permitted development rights are more limited, or removed entirely, in several situations:
- Flats and maisonettes do not have householder permitted development rights, so extensions need planning permission.
- Conservation areas, national parks and other designated land have tighter limits, for example on side extensions and cladding.
- Listed buildings need listed building consent for most alterations, inside and out.
- Article 4 directions allow councils to remove specific permitted development rights in an area.
- Previous planning conditions on your property, or on the estate when it was built, may have removed some rights.
Get it confirmed with a Lawful Development Certificate
Even if your project falls within permitted development, it is worth applying for a Lawful Development Certificate. It is formal confirmation from the council that the work is lawful, which gives you peace of mind and is often requested by buyers’ solicitors when you come to sell.
Planning is only part of the picture
Permitted development deals with planning. You will still need other approvals:
- Building regulations. Almost all extensions need building regulations approval, which covers structure, fire safety, insulation, drainage and ventilation. This comes from your local authority building control team or a registered building control approver.
- Party wall agreements. If you are building on or near a shared wall or boundary, the Party Wall etc. Act 1996 may require you to serve notice on your neighbours, usually one or two months before work starts depending on the type of work.
- Build-over agreements. If a public sewer runs under the footprint of your extension, you may need permission from the water company.
Where to start
Start with a measured survey and a few design options, then check them against the rules before you spend money on detailed drawings. Our design team does exactly this as part of our architectural design and planning service, and we can build the extension too.
Not sure where your project stands? Contact us for a free initial chat and we will tell you which approvals you are likely to need.